Bromont - Launch of new Altitude investment project - Hybrid lift

Recommended Posts

Bromont has just announced their Altitude investment project, with a video highlighting the new summit lodge, as well as the new lift that will be installed to replace the #4 lift on Versant du Village. After earlier discussions that the lift would be a six-passenger chairlift, it is now announced that it will be a 6-passenger chairlift / 8-passenger gondola Hybrid lift. In total, more than $25 million in improvements.

More water slides and zip lines are also shown in the promotional video. Also mentioned are improvements to the main chalet on Versant du Village and to the one on Versant du Lac.

The new waterslide will open in June this year. The new lift will be built by Doppelmayr and open in time for the next ski season 2018-19. The summit chalet will start construction this fall to open the following ski season 2019-20. 

bromont.thumb.png.0f493b0d32c9afdcbcd04ccd8279b10f.png

bromont.JPG.f3bd7313acee96ebf712c8b18055b3e1.JPG

Here is the official press release on the announcement.

https://www.slopeedge.net/content/investments-of-more-than-25-million-at-the-ski-resort-bromont-montagne-d-experiences

Share this post


Link to post

I was out at the Bromont Flea Market today and got a couple of shots of the mountain. The snow is pretty much done but I took a super zoom with my camera of the summit and you'll notice the crane at the top getting ready to take down the upper terminal of the Quad. The towers are still in place for the time being and the cable is off the line. 

IMG_2335.thumb.JPG.4ebd07852e35580884bec419d669ac43.JPG

IMG_2334.thumb.JPG.0e09cfd3fbc0995dae86e27aaec1411f.JPG

Share this post


Link to post

Nice pictures Paul.

Looks like things are progressing well so far. The drive section of the summit terminal appears gone already. I'm sure the Bromont maintenance department won't miss that lift.

Thanks for the photos. I'm disappointing that their webcams are offline, which would have given a great view of the base terminal and what's going on there.

Share this post


Link to post

Here are some update photos from today of the summit at Bromont while at the Flea Market. Pretty amazing difference in about a month. At the Flea Market by the Autoroute, you are still a good 2 to 3 miles away to the summit. These were taken with my Canon SX-510 HS point and shoot camera with a ridiculous zoom on it. 30x optical zoom and these were taken at 60 to 75x digital zoom. 

fullsizeoutput_413.thumb.jpeg.071ab1f63dd31a137a8180755d0e5cfd.jpeg

fullsizeoutput_414.thumb.jpeg.614c50fcb9dac7a0ea88da6e38ed439e.jpeg

 

Share this post


Link to post

Those are great pics Paul. Thanks for sharing them.

They really are following through with their plan to level the summit area, which I find is a good idea. It was always awkward to arrive on one lift and have to loop around like you were on a different step or floor than the other lifts, so it will be good to have it smoothed out finally. Plus I'm sure they need to rework the summit to accommodate the future summit chalet as well.

Share this post


Link to post

Bromont just had a media event to announce the launch of Phase 2 of the Altitude project. Shown on instagram, they have an image that mentions $100 million in investments. More details to follow but here’s the press release on CNW in French. 

https://www.newswire.ca/fr/news-releases/bonification-de-loffre-touristique-du-quebec---un-projet-de-pres-de-76-m-pour-le-developpement-et-la-modernisation-de-bromont-montagne-dexperiences-689907631.html

This second phase of development at Bromont promises an enlargement of the welcome, arrivals and mountain access areas and services on the Versant du Village, as well as the addition of new activites that will enrich the four seasons offerings.

Share this post


Link to post

Bromont have announced the name of the new lift : L'Express du Village.

Here are some stats on the new L'Express du Village lift as provided by Bromont.

  • Capacity of 3220 people per hour.
  • 72 - 6 passenger chairs.
  • 18 - 8 passenger gondola cabins
  • 4 chairs separate each gondola cabin
  • 4 minutes 25 seconds to reach the summit, which is a reduction of 55 seconds from the old lift.

For comparison with the old #4 Versant du Village lift being replaced:

  • Capacity of 2400 people per hour.
  • 108 - 4 passenger chairs.
  • 5 minutes 21 seconds to reach the summit.

Share this post


Link to post

Here is a shot of the summit of the mountain taken Sunday September 23, 2018 from the Bromont Flea Market site. Work is progressing. 

fullsizeoutput_675.thumb.jpeg.2d6d00dc31c269f31eb24c1ccc50ed6c.jpeg

 

Share this post


Link to post

Penseur on Remontees-Mecaniques.net has posted some pictures of the current progress of the new lift.

You can find them here: https://www.remontees-mecaniques.net/forums/index.php?showtopic=12714&view=findpost&p=302197

From the pictures, the bottom terminal is going up, and the enclosure shell for it should be up in a matter of a week or so I would guess. Farther up the line, the towers don't seem to be installed yet. We don't see the summit terminal and it may well be more advanced. If so, it would be more or less around the same point progress wise as the Lowell Thomas at Tremblant.

Share this post


Link to post

I drove by Bromont today on the way to a family party and it looks like the top terminal is going up. I saw some activity up there since the last time I was in Bromont at the flea market. No pics though. Too cloudy to get a decent zoom in shot of it.

Share this post


Link to post

Two weeks ago Bromont posted a construction update video. It shows the new lift going in, the summit and new summit chalet foundations, improvements to some trails (grading and widening) among other things. Its short and sweet, worth watching. Needless to say, the new summit chalet will have a great view of the region.

Important to remember, the new hybrid lift will open this year, the summit chalet will only open the following season.

 

Share this post


Link to post

Here are some screenshots from the Summit webcam. You can clearly see how the top has been greatly flattened from before. The new Hybrid lift and the Versant du Lac quad are now at the same level. Wonder if they will bring the top of the fixed grip Versant du Village quad closer to this area, as it still is a touch downhill from the actual summit and the other two lifts.

Bromont-Sommet.thumb.jpeg.b47dfcd1a144c65d227967a113bed0ac.jpeg

Share this post


Link to post

bromont-summit-dec15-pm.thumb.jpeg.a56c0fcdb22033f75f11c6ae2b134f52.jpeg

The chairs and most gondola cabins appear to be on the line now. Some left to load.

Bromont is aiming to open the new Express du Village lift slightly before Christmas. That gives them another week to finish it up. Today being Saturday, I was checking the webcam and there were people working on the lift and loading more chairs and cabins.

Share this post


Link to post

Bromont held the official inauguration ceremony of the new Express du Village hybrid lift today. After 8 months of work, the lift is finally ready. It will open this coming Sunday at 8:30am to the delight of all skiers and snowboarders.

Here are some photos and video from Bromont's Facebook page from the inauguration. (Credit Bromont facebook page)

48405657_10161346996375595_1866242648222728192_o.thumb.jpg.7afdeaf5b828b6c087515d290a5b9184.jpg

48418223_10161346996455595_3571206577241194496_o.thumb.jpg.1f412d52c63431b0b2ff85089b263049.jpg

48385851_10161346996685595_2249506859494932480_o.thumb.jpg.9f1a5d45b12f7a04f24879e8f555a596.jpg

Here's a recap of some stats on the lift, compared to the old detachable quad it replaces.

The new L'Express du Village lift.

  • Capacity of 3220 people per hour.
  • 72 - 6 passenger chairs.
  • 18 - 8 passenger gondola cabins
  • 4 chairs separate each gondola cabin
  • 4 minutes 25 seconds to reach the summit, which is a reduction of 55 seconds from the old lift.

For comparison with the old #4 Versant du Village lift being replaced:

  • Capacity of 2400 people per hour.
  • 108 - 4 passenger chairs.
  • 5 minutes 21 seconds to reach the summit.

You can read the official news release here : https://www.slopeedge.net/content/inauguration-of-the-new-chairlift-l-express-du-village-at-bromont

And here are some photos from the webcam today, first the morning and then the evening.

bromont-base-dec20-morning.thumb.jpeg.30e6f70a67c23cb3b85eb1c0d91d6cd2.jpeg

bromont-base2-dec20-morning.thumb.jpeg.78e671b0ee86e666cb4e59bc42b160b7.jpeg

bromont-summit2-dec20-morning.thumb.jpeg.cf3e85d20a65382182fedb19dad1554f.jpeg

bromont-summit-dec20-morning.thumb.jpeg.b2154bbd37df6de77da74b9237203a2e.jpeg

bromont-base-dec20.thumb.jpeg.1f5e1f3912e74d6d2845f83029d07526.jpeg

bromont-summit-dec20.thumb.jpeg.a2bcbdedefcad8a3e232aa522cf0e2a7.jpeg

bromont-summit2-dec20.thumb.jpeg.a922ef82f3f0cf2a0902ba230e076b30.jpeg

Don't forget... just to the side of this new lift... a summit chalet will rise for the following ski season. Big changes at Bromont to come over the next years, this is only the start!

Share this post


Link to post

Update: so apparently the Chondola opened, and then promptly closed due to some issue. It was "indefinitely" closed but is now reopened. Perhaps a trip is in order :)

Share this post


Link to post

Seems like the new lift has been running into some issues. Again it is closed now for the past couple days. Not sure what is going on, hoping they can get things working at 100% soon.

It doesn't need to be said that this is the most advanced lift in Quebec, and as such it is a complicated piece of machinery and pieces that operate at a very specific timing and speed. I don't doubt it will be reliable very soon, but it is something that takes time to achieve.

Share this post


Link to post

Yeah my friend was there the other night and she said people were stuck on it for 1.5 hours!!!! And that night was cold, but at least not cold like tonight. Imagine being stuck on the chair in this weather, ick. I'm sure it'll get sorted. I honestly expected some lift glitches which is perhaps why I haven't hightailed it out to Bromont to activate my pass yet. I had honestly planned to avoid the chodola altogether and stick to the super slow old lift, it's always a nice ride anyways.

Share this post


Link to post

Your content will need to be approved by a moderator

Guest
You are commenting as a guest. If you have an account, please sign in.
Reply to this topic...

×   Pasted as rich text.   Restore formatting

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

Loading...

  • Similar Content

    • By Shane
      It's the beginning of March Break in Quebec, the weather is warming up, and spring skiing has had an early start. Today's destination was Bromont, a place I really enjoy but had not visited in 5 years. The weather was mild, hovering around and above 0 degrees Celsius.
      Heading up from Ottawa, the 3-hour drive goes quickly thanks to the route being made up entirely of highways. The 'new' highway 30 that bypasses downtown Montreal is completely worth the $2.80 toll required to use it.
      Arriving at Bromont shortly before 11 am, the main parking is about half full, and the chalet has plenty of seats and tables free. After quickly getting ready, I headed out to start off on the classic Versant du Village, one of Bromont's 7 hillsides. The ride up the mountain's 385m of vertical goes quickly on the #4 chairlift, which is finishing its final year of service. It is to be replaced by a new six-passenger chairlift in time for next season.

      The mountain has trails suitable for all skill levels, from beginner slopes to expert terrain. Versant du Village has it all, from the tame Brome to the Coupe du Monde trail.
      Bromont has over 100 trails, and it is impossible to experience all that the mountain has to offer in one visit, there is just too much. Wanting to make the most of my visit, I set out to experience one or two trails per hillside.
      Starting off with Versant de la Côte Ouest.


      Next, the Versant du Midi.

      Versant des Epinettes.


      Versant du Lac.

      Versant du Village.




      A quick pause in the chalet for lunch, with some tasty paninis and some traditional poutine, then back out on the trails to visit Mont Soleil. This separate part of the mountain is home to the main beginner trails and learning area. It is also bordered by many homes, condos and ski chalets, and gives great views of the Versant du Village nearby. (Sorry, I didn't snap any pictures this visit).
      Scooting over to Versant des Cantons, which I almost forgot this visit...


      Overall, conditions were excellent. As the mountain has 7 hillsides in all directions, the ski conditions were different all over based on the orientation with the sun. Mainly it was spring skiing, due to the soft and forgiving snow. Several trails also had nice moguls and bumps forming, which I am sure pleased a lot of people.
      Main Summit of Versant du Village and Versant du Lac.

      One area that I particularly like is the summit of Versant du Village. It is very small, so small that no sooner do you get off the chairlift, you are already coming back down. This gives the unique thrill of being at the very top of the mountain. 
      Bromont is a great mountain to visit and discover. The facilities are modern and well maintained. Many slopes are re-groomed during the day to refresh the ski conditions. Plenty of trails and hillsides ensures you never get bored. You really can't go wrong. With the town of Bromont only minutes away, there are plenty of hotels, restaurants, and even factory outlets to round out your visit. 
      With a new chairlift coming next season, and plenty of trails still waiting to be discovered, I can't wait for my next visit.
      Happy Skiing. 

    • By Shane
      Chairlift #4 (the main detachable quad on the Versant du Village) has been out of service since Tuesday/Wednesday last week. The cause is vibrations/oscillations and noise from the bull wheel at the summit. Not wanting to take any chances, the lift is being inspected to determine the cause and repaired. Already the bull wheel has been removed and moved to the base of the mountain for repairs.
      You can see more in this great video Bromont created about what's going on, attached below.
      Earlier on this winter, the Quebec government announced support and investment into Bromont, which included some funding for a new six-pack chairlift. No doubt, this lift is for the Versant du Village, to replace the #4 lift. While no further details have come out, and due to the fact that they also mention at the time a summit chalet will be constructed in the near future, it is possible that this new lift could be a Hybrid lift like at Orford, consisting of six-pack chairs and gondola cabins.
      Either way, let's hope this all comes to pass over the summer and fall so that skiers are treated to a more reliable lift. The #4 lift is the primary lift of the mountain and among the absolute first generation of detachable quad chairlifts. It has served it's time and has reached the point of replacement.
      What are your thoughts? Have you heard any rumors or have any news to share?
×